The team at Windermere Estate have continued their progress, in particular the Ison Road/ Plane Avenue Intersection: Just one of many areas the team are working on across Risland’s multi-stage development!
Works undertaken include:
Over 15,000 m3 of cut/ fill works completed in this portion
Over 600 lm of drainage works
Over 6,000 tonnes of asphalt
Over 15,000 tonnes of pavement materials
Over 2,000 lm of kerb concrete works
Over 300 m3 of concrete pedestrian and bicycle path
Installation of electrical road crossing over 3m depth under twin 1200mm drainage line
A big shout out to UCS (Electrical), Downer (Asphalt) and Healeys Infrastrucure (Traffic Signals) who assisted us in reaching practical completion a few weeks ago.